A week of training
Fabric 10Keep every goal green in each wave.
Goals
Not tested yet
16 H100 train a 13B model for a week; a third server waits idle. A GPU, a rail switch and a whole server will fail. Set the checkpoint plan and the spare pool before the run: the job must be productive 96.5 percent of the week and lose at most 40 min of work in a failure.
Backup every 60 minutes · RPO 60 minutes · RTO 11 hours at 100 Mbps